Generating stations 17
Question = A run of river hydroelectric plant with pondage has the following data ; installed capacity = 10 MW , water head , H = 20 meter , efficiency overhaul = 80% , load factor = 40% ,
(1) determine the river discharge in m³/sec. required for the plant , (2) if on a particular day , the river flow is 20 m³/sec. , What load factor can the plant supply ?
Solution = consider the duration to be of one week unit generated / week = max demand × L.F. × hours in a week ,
» (10 × 10³) × (0.4) × (24×7) kWh = 67.2 ×10⁴ kWh. (1)
» let Q m³/sec. be the rever discharge required =
» weight of water available/sec. , W = Q × 9.81 × 1000 , = 9810 Q Newtown (N) ,
» average Power produced = W × H × η overall , = 9810 Q × 20 × 0.8 W , = 156960 Q watt , or , 156.96 Q Kw
» ( 24 hours × 7 days = 168 hours )
» unit generated/week = 156.86 Q × 168 kWh , = 26369 Q kWh (2)
» equations (1) and (2) , We get ,
» 26,369 Q = 67.2 × 10⁴ , = Q = 67.2 × 10⁴ /26369 , = 25.48 m³/sec , answer ✓
(2) formula ,
» load factor = unit generated on that day kilowatt ÷ 10⁴ × hour in on day ,
» unit generated on that day = power developed × 24 ,
» power developed = average Power produced × river discharge , = 156.96 ×20 , = 3139.2 kw ,
» unit generated on that day = 3139.2 kw × 24 = 75341 kWh ,
»( 10 MW = 10000 kw , or , 10⁴ kw )
» So , load factor =( 75341/10⁴ × 24 ) × 100 , = 31.4 % , answer ✓
Comments
Post a Comment